1) Please bare with me as I am NOT an electrician. I am seeking help, knowledge, guidance for my current setup.
2) I had an electrician help me wire it and the current diagram is basically how it is currently wired. Please keep in mind the colors don't have much significance, except green is GND, black/red are for where they are on the bus bar or the receptacle I believe is correct, the Blue is Neutral/Common as I think its referred to. Due to life changes/events its taken me about 3 years to get back to this project.
3) After completing the current schematic (see attached) I have noticed that the relays for the the 2x Gas transformers are also connected to a receptacle which they should NOT be, the receptacles should power on 2 pumps instead. The transformers are NOT wired at all. the switch for the gas is actually a "Latching Rotary Select Selector Switch - ON-NONE-OFF" intent was for manual override/safety.
4) I have recently verified that with the Brewpi software & the expansion boards to the relay boards all this works in software and does turn the relay on/activates it.
5) Currently I believe because the wiring for the gas is incorrect for my application/intent this is causing some sort of issue to where I do not have 120V out.
6) My hope or intent is to correct how it is currently wired for the gas, I can then wire the transformers into the relays, and provide an updated schematic after that has been corrected. I'm a very visual person so usually drawings or circle highlights etc. to point out what needs to be corrected is likely best way to go.
7) I'm sure there will be questions along the way, I will do my best to answer them to the best of my knowledge.
thank you in advance,
2) I had an electrician help me wire it and the current diagram is basically how it is currently wired. Please keep in mind the colors don't have much significance, except green is GND, black/red are for where they are on the bus bar or the receptacle I believe is correct, the Blue is Neutral/Common as I think its referred to. Due to life changes/events its taken me about 3 years to get back to this project.
3) After completing the current schematic (see attached) I have noticed that the relays for the the 2x Gas transformers are also connected to a receptacle which they should NOT be, the receptacles should power on 2 pumps instead. The transformers are NOT wired at all. the switch for the gas is actually a "Latching Rotary Select Selector Switch - ON-NONE-OFF" intent was for manual override/safety.
4) I have recently verified that with the Brewpi software & the expansion boards to the relay boards all this works in software and does turn the relay on/activates it.
5) Currently I believe because the wiring for the gas is incorrect for my application/intent this is causing some sort of issue to where I do not have 120V out.
6) My hope or intent is to correct how it is currently wired for the gas, I can then wire the transformers into the relays, and provide an updated schematic after that has been corrected. I'm a very visual person so usually drawings or circle highlights etc. to point out what needs to be corrected is likely best way to go.
7) I'm sure there will be questions along the way, I will do my best to answer them to the best of my knowledge.
thank you in advance,